US Navy Cruisers — CG (Ticonderoga class)
Cruisers worksheet  ·  Data as of 3 Oct 2026  ·  15 corrections applied · NAVADMIN 099/26
5 Active 22 Inactive 27 built 1983–1994 All decommissioning by FY2028
Active cruisers (as of 3 Oct 2026)
5
Of 27 built (CG-59,62,64,65,71)
Inactive / decommissioned
22
CG-67 & CG-70 decommissioned Sep 2026
Class total built
27
1983–1994 · Ingalls: 19 · BIW: 8
Last active ships
FY2028
CG-59, 62, 64, 65 planned FY2027 · CG-71 FY2028 (PB27 plan, May 2026)
2026
Ingalls active
—
BIW active
—
▲ Total active cruisers
—
Decommissioned by this date
—
Active cruiser homeports (as of 3 Oct 2026)
5 active ships, 3 homeports
Builder breakdown — all 27 ships
Ingalls Shipbuilding (Pascagoula) vs Bath Iron Works
Commissionings by year
27 ships commissioned 1983–1994
Decommissionings by year
Progressive retirement 2004–2030
Keel-to-delivery (C→D) by ship
Months from keel laying to delivery. Colored by builder.
Overall median: 29.9 mo (2.5 yrs)
Ingalls median: 28.5 mo
BIW median: 32.8 mo
Award-to-delivery (A→D) by ship
Months from contract award to delivery.
Overall median: 57.9 mo (4.8 yrs)
Cruiser service life timeline — all 27 ships
Commission to decommission. Use the date slider on Overview to move the needle.
Hull Name Status Fleet Homeport Award Keel Launched Christened Commissioned Delivery Decomm date Decomm yr C→D mo A→D mo Builder Callsign
Data as of 3 Oct 2026 · Battle force counted per SECNAVINST 5030.8D (from delivery until decommissioning; nuclear ships until start of inactivation) · Projected dates and placeholders are flagged in the data download · Sources: Naval Vessel Register, Navy/NAVSEA/MSC releases, PB27 Shipbuilding Plan & SCN justification book, CRS, USNI News · Download data (CSV)