US Navy Destroyers — DDG
Destroyers worksheet  ·  Data as of 3 Oct 2026  ·  3 corrections applied
79 Active 8 Under Construction 15 Authorized Arleigh Burke & Zumwalt
Active destroyers
79
Arleigh Burke: 77 · Zumwalt: 2
Under construction
8
DDG-126, DDG-129, DDG-130, DDG-131, DDG-132, DDG-133, DDG-134, DDG-1002
Authorized
15
DDG-135 through DDG-149
Total program
102
Arleigh Burke: 99 · Zumwalt: 3
2026
Arleigh Burke active
—
Zumwalt active
—
▲ Total active
—
Under construction
—
Active destroyers by homeport
79 active ships, 7 homeports
Arleigh Burke active ships by flight
Flight I: 21 · Flight II: 7 · Flight IIA: 46 · Flight III: 3
Commissionings by year
Arleigh Burke class — 1991 to present
Active ships by builder
Bath Iron Works vs Ingalls Shipbuilding
Keel-to-delivery (C→D) by ship — Arleigh Burke class
Months from keel laying to delivery. Colored by flight. Dashed lines = class median per flight.
Flight I median: 28.7 mo
Flight II median: 25.3 mo
Flight IIA median: 29.3 mo
Flight III median: 47.4 mo
Award-to-delivery (A→D) by ship — Arleigh Burke class
Months from contract award to delivery. Dashed lines = class median per flight.
Flight I median: 62.5 mo
Flight II median: 61.4 mo
Flight IIA median: 74.75 mo
Flight III median: 103.9 mo
Destroyer service life timeline
Commission year to planned decommission — all Arleigh Burke & Zumwalt ships. Use the date slider on Overview to move the needle.
Hull Name Class Flight Status Fleet Homeport Award Keel Launched Christened Commissioned Delivery Decomm yr Builder Callsign
Data as of 3 Oct 2026 · Battle force counted per SECNAVINST 5030.8D (from delivery until decommissioning; nuclear ships until start of inactivation) · Projected dates and placeholders are flagged in the data download · Sources: Naval Vessel Register, Navy/NAVSEA/MSC releases, PB27 Shipbuilding Plan & SCN justification book, CRS, USNI News · Download data (CSV)