US Navy Frigates — FFG (Constellation class)
Frigates worksheet  ·  Data as of 3 Oct 2026  ·  Updated with post-snapshot program changes
2 Under Construction 4 Cancelled Nov 2025 FF(X) program launched Dec 2025
⚠
Major program restructuring — Nov–Dec 2025: SECNAV Phelan cancelled the last four authorized Constellation-class ships (FFG-64 through FFG-67) on November 25, 2025. Only FFG-62 Constellation and FFG-63 Congress will be completed (both at Fincantieri Marinette Marine, WI). A replacement FF(X) program based on the NSC Legend-class hull was announced December 19, 2025; HII/Ingalls awarded a $282.9M lead-yard contract April 28, 2026. FFG-62 delivery slipped from April 2026 to April 2029 (36-month delay, ~12% complete as of Nov 2025).
Under construction
2
FFG-62 Constellation · FFG-63 Congress
Cancelled (Nov 2025)
4
FFG-64 through FFG-67 — none had begun construction
FFG-62 completion
~12%
Latest public figure (Nov 2025) · delivery TBD — under Navy review per PB27 budget (Apr 2026)
FF(X) replacement
2030
FF(X) 1 projected delivery Jun 2030 (PB27 SCN) · award Mar 2027 · HII Ingalls
Program status breakdown
All 26 FFG hull numbers (FFG-62 through FFG-87)
Projected commissioning schedule (surviving hulls)
FFG-62 and FFG-63 only — all others cancelled or unplanned
Constellation-class vs FF(X) — key comparison
Why the Navy pivoted away from the Constellation class
Constellation class (FFG-62) — cancelled
• Based on Italian-French FREMM design (15% commonality achieved vs 85% goal)
• Displacement: ~8,000 tons full load
• Builder: Fincantieri Marinette Marine (WI)
• Contract: $5.6B for up to 10 ships (FPI)
• Lead ship 36 months late, 759 tons overweight
• "80% the cost of a DDG-51, 60% the capability" — SECNAV Phelan
• Design not finalized before construction started
FF(X) program — replacement
• Based on HII Legend-class NSC (proven design, 10 built for USCG)
• Displacement: ~4,500 tons (substantially smaller)
• Builder: HII/Ingalls Shipbuilding (Pascagoula, MS) — sole source
• $282.9M lead-yard contract awarded Apr 28, 2026
• First hull in water target: 2028
• FY2027 budget: 1 ship; FY2029: 1 ship; FY2031: 2 ships
• Competition for additional hulls planned at other yards
Constellation class & FF(X) — program timeline
Key milestones from award to projected delivery
Hull Name Status Award date Keel laid Proj comm yr Builder Homeport
Data as of 3 Oct 2026 · Battle force counted per SECNAVINST 5030.8D (from delivery until decommissioning; nuclear ships until start of inactivation) · Projected dates and placeholders are flagged in the data download · Sources: Naval Vessel Register, Navy/NAVSEA/MSC releases, PB27 Shipbuilding Plan & SCN justification book, CRS, USNI News · Download data (CSV)